Bydgoszcz, Poland
City population: 352085
Duration: unknown – 2019
Implementation status: Completed
Scale: Micro-scale: District/neighbourhood level
Project area: 3000 m2
Type of area: Natural Heritage Area/Untouched nature
Last updated: October 2021

The revitalization of two parks in Bydgoszcz - on 'Dabrowski’ and 'Liberty’ hills was planned in 2016 and successfully implemented in 2019. The project involved greenery planting, building health paths and outlook points, as well as new benches and a playground. It improved the aesthetic qualities of the parks, supported the effective management of rainwater and reduced noise from the surrounding areas [1].

Overview

Nature-based solution

  • Parks and urban forests
  • Large urban parks or forests

Key challenges

  • Water management (SDG 6)
  • Stormwater and rainfall management and storage
  • Green space, habitats and biodiversity (SDG 15)
  • Green space creation and/or management
  • Environmental quality
  • Noise reduction
  • Regeneration, land-use and urban development
  • Promote natural styles of landscape design for urban development
  • Health and well-being (SDG 3)
  • Enabling opportunities for physical activity
  • Creation of opportunities for recreation

Focus

Maintenance and management of urban nature, Transformation of previously derelict areas

Project objectives

1) Improving aesthetics of the parks; 2) Improving rainwater management in both parks; 3) Providing access to a modernized green urban area for the citizens, including a safe hillside [1].

Implementation activities

1) Revitalization of the park, including the hillside of the Liberty Hill – 3000 m2 [1] 2) Building a cycling-walking route on the 1/3 of the hillside area, and separate walking and cycling routes on the remaining area [2] 3) Improving rainwater management in both parks; 4) Greenery planting; 5) Building health paths and outlook points; 6) Assembly of new benches; 7) Introducing rubbish bins and new playground equipment [1].

Main beneficiaries

  • Local government/Municipality
  • Citizens or community groups

Governance

Management set-up

  • Government-led

Type of initiating organisation

  • Local government/municipality

Participatory approaches/ community involvement

  • Unknown

Details on the roles of the organisations involved in the project

The local government has developed plans for the revitalization of two parks and applied for the EU funds for the project's implementation.

Project implemented in response to ...

... an EU policy or strategy? Unknown
... a national policy or strategy? Unknown
... a local policy or strategy? Yes (The revitalization of the park on the "Freedom Hill" can only be conducted in line with the local land development plan for the "Freedom Hill" (Wzgórze Wolności), and the latter states that any works in the park need to preserve the existing gorges and ravines and do not intervene in their natural formation.(2))

Financing

Total cost

€500,000 - €2,000,000

Source(s) of funding

  • EU funds
  • Public local authority budget

Type of funding

  • Earmarked public budget
  • Direct funding (grants, subsidies, or self-financed projects by private entities)

Non-financial contribution

Unknown

Impacts and Monitoring

Environmental impacts

  • Green space and habitat
  • Increased green space area
  • Increased conservation or restoration of ecosystems
  • Reduced biodiversity loss
  • Increased number of species present
  • Enhanced support of pollination
  • Increased ecological connectivity across regeneration sites and scales
  • Restoration of derelict areas

Economic impacts

  • Unknown

Socio-cultural impacts

  • Safety
  • Increased perception of safety
  • Social justice and cohesion
  • Improved access to urban green space
  • Health and wellbeing
  • Gain in activities for recreation and exercise
  • Cultural heritage and sense of place
  • Protection of natural heritage
  • Increased awareness of flora and fauna as culturally and historically meaningful
  • Education
  • Increased awareness of NBS and their benefits

Type of reported impacts

Expected impacts, Achieved impacts

Presence of formal monitoring system

Unknown

Presence of indicators used in reporting

No evidence in public records

Presence of monitoring/ evaluation reports

No evidence in public records

Availability of a web-based monitoring tool

No evidence in public records

References

Revitalizations in Bydgoszcz
Source: https://www.bydgoszcz.pl/aktualnosci/tresc/park-na-wzgorzu-wolnosci-odzyskuje-blask/